The Ivy House

See properties >>>> building progress exteriors interiors floor plans
 
IVY HOUSE   Friday, May 31st 2013


Building work schedule:

13-Aug-2012 - Building permit granted

14-Aug-2012 - Start of construction work

28-Aug-2012 - Foundations stage - completed

22-Sep-2012 - Level 1 & Level 2 - completed

16-Oct-2012 - Level 3 & Level 4 - completed

27-Oct-2012 - Level 5 - completed

30-Nov-2012 - Outside walls - completed

18-Dec-2012 - double glazing, windows and doors - completed

27-Dec-2012 - start of internal works

10-Mar-2013 - External walls cladding and Roof - completed 

25-May-2013 - Balcony balustrades, pathways and landscaping - completed

 

 

31-July-2013 - Completion